City of Morgan Hill Capital Improvement Program FY 2024-25 – FY 2029-30
Project Name: Non- Profit Center
Project No. PR1014
Project Location
Financial Comments No funds have been expended on this project in previous fiscal years, however, $810,000 is allocated in FY 2023 -24 for the required purchase of the building.
Community and Cultural Center
Operating Cost Impacts The City will require non-profits or other recreational use or rental of the new facility to cover all costs associated with the facility, which will result a positive net impact on the General Fund.
Expenditure Schedule Annual Expenditures
2024-25
2025-26
2026-27
2027-28
2028-29
2029-30
Fund-360
500,000
-
-
-
-
-
$ 500,000
-
-
-
-
-
Project Cost
Estimated Project Schedule
Timeline for Completion
Complete Complete
Planning
Project Design
Right of Way/ Acquisition/Permitting
Complete
Construction
In Progress. Tenant Improvements FY2024-25
Project Close-out
FY 2024-25 & 2025-26