Adopted Capital Improvement Program Budget FY 2024-25 through FY 2029-30
City of Morgan Hill Capital Improvement Program FY 2024-25 – FY 2029-30
Project Name : Traffic Signal and Intersection Improvements Project No. SR5003
Project Location
Financial Comments Funding for these improvements is obtained through the collection of traffic impact fees from developers. Future project funding for FY 2026-27 and later will be identified through the Transportation Master Plan, which is currently in development. Operating Cost Impacts New signals and improvements increase operating
Various Intersec�ons
costs for the Streets Maintenance Division. Additionally, signal maintenance costs are approximately $2,500 each annually.
Expenditure Schedule Annual Expenditures
2024-25
2025-26
2026-27
2027-28
2028-29
2029-30
Fund-309
1,500,000
3,000,000
-
-
-
-
Project Cost $ 1,500,000 $ 3,000,000
-
-
-
-
Estimated Project Schedule
Timeline for Completion
In progress FY 2024-25
Planning
Project Design
Right of Way/ Acquisition/Permitting
Not applicable
Construction
FY 2025-26 FY 2026-27
Project Close-out