City of Morgan Hill Adopted Budget FY 2016-17 and FY 2017-18

CITY OF MORGAN HILL CAPITAL IMPROVEMENT PROGRAM

Water

Project Title

2016-17

2017-18

2018-19

2019-20

2020-21

2021-22

Totals

601000 - New Well Property/Construction 602000 - New Water Reservoirs 603000 - New Water Mains 607000 - Booster Pump Rehabilitation 608000 - Rehabilitate Water Wells 610000 - Water Main Replacement 620007 - Recoat Water Reservoir/Tank 623014 - Water Supply Planning

$1,963,000

$1,140,000

$90,000

$3,193,000

$2,720,000

$370,000

$3,090,000

$1,325,000

$200,000

$200,000

$200,000

$200,000

$2,125,000

$313,000

$1,100,000

$1,413,000

$580,000

$630,000

$1,210,000

$735,000

$735,000

$430,000

$1,100,000 $3,000,000

$200,000

$200,000

$100,000

$100,000

$300,000

$250,000

$250,000

$50,000 $1,050,000

625016 - Well Demolition and Abandonment

$400,000

$400,000

Totals

$7,001,000

$500,000

$1,235,000

$2,955,000

$1,250,000 $2,740,000 $15,681,000

Project Funding Sources

2016-17

2017-18

2018-19

2019-20

2020-21

2021-22

Totals

651 - Water Impact 653 - Water Capital Project

$3,867,000

$100,000

$300,000 $1,390,000

$250,000

$340,000 $6,247,000

$3,134,000

$400,000

$935,000

$1,565,000 $1,000,000 $2,400,000 $9,434,000

Totals

$7,001,000

$500,000

$1,235,000

$2,955,000

$1,250,000 $2,740,000 $15,681,000

2017-2022 Six-Year Capital Improvement Program

PAGE : 12 OF 123