CITY OF MORGAN HILL CAPITAL IMPROVEMENT PROGRAM
of all phases is estimated to be $5.1 million.
Project Justification The expansion and tenant improvement program is required to meet the future library and community service needs of the Morgan Hill community. The Library was opened in 2007 and has seen a growing demand in children's programs and adult reading areas that cannot be met in the space provided within the existing facility. In addition, after having a few years of operating experience, the staff at the Library has identified better and more efficient uses of the space inside the existing facility that will require reconfiguration.
Expenditure Schedule & Category
Public Facilities: 251015
2016-17
2017-18
2018-19
2019-20
2020-21
2021-22
86200 - Professional Services 86201 - Environmental Clearances 86220 - Architecture and Design
$200,000
$10,000 $65,000
$20,000
86360 - Construction
$3,000,000
86530 - Project Implementation
$40,000 $115,000
$110,000
PROJECT COST
$3,330,000
Funding Source(s)
2016-17
2017-18
2018-19
2019-20
2020-21
2021-22
f348 - Library Impact Fund
$115,000 $3,330,000
FUNDING TOTALS
$115,000
$3,330,000
Estimated Project Schedule 2016-17
2017-18 2021-22 Quarter 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 2018-19 2019-20 2020-21
_______
Planning
__________
Project Design
Right-of-Way Acquisition & Permitting Construction
__________
__
Project Closeout
Operating Cost Impacts The County is responsible for interior expense and responsible to pay for any increase.
2017-2022 Six-Year Capital Improvement Program