City of Morgan Hill Adopted Budget FY 2016-17 and FY 2017-18
CITY OF MORGAN HILL CAPITAL IMPROVEMENT PROGRAM
Project Justification Local flooding can cause damage to public and private property and may present safety issues.
Expenditure Schedule & Category
Storm Drainage: 415097
2016-17
2017-18
2018-19
2019-20
2020-21
2021-22
86220 - Architecture and Design
$40,000
$10,000 $120,000 $20,000 $150,000
$10,000 $120,000 $20,000 $150,000
$10,000 $120,000 $20,000 $150,000
$10,000 $120,000 $20,000 $150,000
$10,000 $120,000 $20,000 $150,000
86360 - Construction
86530 - Project Implementation
$10,000 $50,000
PROJECT COST
Funding Source(s)
2016-17
2017-18
2018-19
2019-20
2020-21
2021-22
f304 - Drainage (NonAB1600) Fund
$50,000 $50,000
$150,000 $150,000
$150,000 $150,000
$150,000 $150,000
$150,000 $150,000
$150,000 $150,000
FUNDING TOTALS
Estimated Project Schedule 2016-17
2017-18 2021-22 Quarter 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 2018-19 2019-20 2020-21
_____
_____
_____
_____
_____
_____
Planning
__
__
__
__
__
__
Project Design
Right-of-Way Acquisition & Permitting Construction
__
__
__
__
__
__
Project Closeout
Operating Cost Impacts As local drainage problems are repaired or improved, maintenance costs are reduced during rain events.