CITY OF MORGAN HILL CAPITAL IMPROVEMENT PROGRAM

Project

Project No.

315006

New Sewer Mains

Category

Wastewater

Department

Public Works

Council Priorities Enhancing Public Safety, Maintaining Fiscal Responsibility

Location

Citywide

Project Description In FY 16/17, a new sewer main on Railroad between Barrett and Tennant will be installed. A new sewer main on Tennant between Railroad and Monterey will be designed and constructed in FY 17/18.

FY 16/17: Railroad Ave: between Barrett & Tennant FY 17/18: Tennant: between Railroad & Monterey Rd FY 17/18: Tennant: Railroad Crossing

A new CIP is being prepared as part of the new Water Master Plan to be completed in early FY 16/17. Future sewer main projects will be defined including scope and timing of the projects in the new CIP. The spending plan above will be updated once the new project schedule is defined.

Project Justification New sewer mains are required to provide adequate capacity and support development-related growth.

2017-2022 Six-Year Capital Improvement Program

PAGE : 74 OF 123