CITY OF MORGAN HILL CAPITAL IMPROVEMENT PROGRAM
Expenditure Schedule & Category
Water: 601000
2016-17
2017-18
2018-19
2019-20
2020-21
2021-22
86200 - Professional Services 86220 - Architecture and Design
$35,000 $193,000
$114,000 $969,000
86360 - Construction
$1,639,000
86530 - Project Implementation
$96,000
$57,000
$90,000 $90,000
PROJECT COST
$1,963,000
$1,140,000
Funding Source(s)
2016-17
2017-18
2018-19
2019-20
2020-21
2021-22
f651 - Water Impact Fund
$1,963,000 $1,963,000
$1,140,000 $1,140,000
$90,000 $90,000
FUNDING TOTALS
Estimated Project Schedule 2016-17
2017-18 2021-22 Quarter 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 2018-19 2019-20 2020-21
_____
Planning
__
_____
Project Design
Right-of-Way Acquisition & Permitting Construction
__________
_______
__
Project Closeout
Operating Cost Impacts This project will increase maintenance and operating costs which will be offset by increase in revenues from new users.
2017-2022 Six-Year Capital Improvement Program