City of Morgan Hill Adopted Budget FY 2016-17 and FY 2017-18
CITY OF MORGAN HILL CAPITAL IMPROVEMENT PROGRAM
Expenditure Schedule & Category
Water: 603000
2016-17
2017-18
2018-19
2019-20
2020-21
2021-22
86200 - Professional Services 86220 - Architecture and Design
$35,000
$25,000 $160,000 $15,000 $200,000
$25,000 $160,000 $15,000 $200,000
$25,000 $160,000 $15,000 $200,000
$25,000 $160,000 $15,000 $200,000
86360 - Construction
$1,221,000
86530 - Project Implementation
$69,000
PROJECT COST
$1,325,000
Funding Source(s)
2016-17
2017-18
2018-19
2019-20
2020-21
2021-22
f651 - Water Impact Fund f653 - Water CIP Fund
$884,000 $441,000 $1,325,000
$200,000
$200,000
$200,000
$200,000
FUNDING TOTALS
$200,000
$200,000
$200,000
$200,000
Estimated Project Schedule 2016-17
2017-18 2021-22 Quarter 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 2018-19 2019-20 2020-21
__
Planning
_____
Project Design
Right-of-Way Acquisition & Permitting Construction
_____
_____
_____
_____
_____
__
Project Closeout
Operating Cost Impacts This project will increase maintenance and operating costs which will be offset by water sales in some instances.