City of Morgan Hill Adopted Budget FY 2016-17 and FY 2017-18
CITY OF MORGAN HILL CAPITAL IMPROVEMENT PROGRAM
Expenditure Schedule & Category
Streets & Roads: 568014
2016-17
2017-18
2018-19
2019-20
2020-21
2021-22
86360 - Construction
$40,000 $40,000
$40,000 $40,000
$40,000 $40,000
$40,000 $40,000
$40,000 $40,000
$40,000 $40,000
PROJECT COST
Funding Source(s)
2016-17
2017-18
2018-19
2019-20
2020-21
2021-22
f346 - Public Facilities (NonAB1600) Fund
$40,000
$40,000
$40,000
$40,000
$40,000
$40,000
FUNDING TOTALS
$40,000
$40,000
$40,000
$40,000
$40,000
$40,000
Estimated Project Schedule 2016-17
2017-18 2021-22 Quarter 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 2018-19 2019-20 2020-21
__
__
__
__
__
__
Planning
Project Design Right-of-Way Acquisition & Permitting Construction
_____
_____
_____
_____
_____
_____
__
__
__
__
__
__
Planning
Operating Cost Impacts This project directly addresses maintenance needs. In addition, the slurry sealing of asphalt protects the surface from water, extends its life, and reduces long-term maintenance expenses.
2017-2022 Six-Year Capital Improvement Program
PAGE : 57 OF 123
Made with FlippingBook