City of Morgan Hill Adopted Budget FY 2016-17 and FY 2017-18
CITY OF MORGAN HILL CAPITAL IMPROVEMENT PROGRAM
Expenditure Schedule & Category
Streets & Roads: 575015
2016-17
2017-18
2018-19
2019-20
2020-21
2021-22
86220 - Architecture and Design
$30,000 $30,000
PROJECT COST
Funding Source(s)
2016-17
2017-18
2018-19
2019-20
2020-21
2021-22
f309 - Traffic Impact Fund
$15,000 $15,000
f346 - Public Facilities (NonAB1600) Fund
FUNDING TOTALS
$30,000
Estimated Project Schedule 2016-17
2017-18 2021-22 Quarter 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 2018-19 2019-20 2020-21
Planning Project Design
__
Right-of-Way Acquisition & Permitting Construction Project Closeout
__
Operating Cost Impacts There are no operating budget impacts.
2017-2022 Six-Year Capital Improvement Program
PAGE : 63 OF 123