CITY OF MORGAN HILL CAPITAL IMPROVEMENT PROGRAM
NEEDED-BUT-NOT-FUNDED PROJECTS Needed-but-not-funded CIP projects are those for which no funding sources are currently available, yet which are described as needed within the General Plan, within the Master Plans (for Storm Drainage, Sewer, and Water), and within other planning documents. The projects are listed so that they can be tracked in the event that funding does become available. This listing also keeps these projects visible as other alternative funding options and other competing projects are being considered. Note: List is not in priority order.
Item # Project Category
Project Description
Estimated Amount
Parks & Recreation 1 Parks Facilities
Butterfield Blvd Linear Park, Phase IV
$1,250,000 $250,000 $17,500,000 $1,000,000
2 3 4 5 6 7
Parks Facilities Parks Facilities Parks Facilities Parks Facilities Parks Facilities Parks Facilities
Community Garden Relocation
Ball Field Development
Outdoor Sports Center Turf Replacement
Unfunded Park Replacement
$590,000 Annually
Future Trail Planning Future Park Acquisition
TBD* TBD*
* up
* Upon completion of Master Plan Update Total
$20,590,000
Public Facilities
8 9
Public Facilities Public Facilities Public Facilities
Morgan Hill Library Expansion, Phase III
$1,600,000 $1,020,000
Corp Yard Improvements
10
Unfunded Building Replacement
$510,000 Annually
Total
$3,130,000
Storm Drainage
11 12 13
Storm Drain Storm Drain Storm Drain
Llagas Rd. between Castle Ridge Dr. & Glen Ayre Dr.
$300,000 $500,000 $150,000 $950,000
Mission View Dr. & Half Rd. Spring St. & Bisceglia Ave.
Total
Streets & Roads
14 15 16
Streets & Roads Streets & Roads Streets & Roads
Pavement Rehabilitation Program
$4,500,000 Annually $9,450,000 70% of Total
Hale Avenue Extension
Butterfield Blvd. North Extension
$1,200,000 $15,150,000 $1,422,000 $593,000 $551,000 $89,000 $829,000 $1,096,000 $400,000 $6,130,000 $125,000 $1,025,000
Total
Water
17 18 19 20 21 22 23 24 25
Water Water Water Water Water Water Water Water Water
Hill Booster: E. Dunne Dr.
Woodland: 2nd Tank
Barrett: Between Condit and Murphy W. Main P/M Booster to DeWitt Dewitt: Between Main & Spring Encinos Booster: Remove From System
Copper Hill: Butterfly & Holiday
Recoat: Jackson Oaks, El Toro, Encino
Solar: San Pedro Well
Total
Total
$45,950,000