CITY OF MORGAN HILL Capital Improvement Program

3. Repair & Replacements (Groups 1-9) The 2017 Sewer SystemMaster Plan identified various rehabilitation and replacement improvements throughout the City. These projects were further classified into specific groupings based on location. Project Justification 1. Compliance Inspections and Repairs The City proactively works to maintain the general condition of the existing sewer system and works to identify areas out of compliance with the existing design and construction standards as well as areas requiring repair. This project is intended to mitigate areas of concern within the sewer system. 2. Pipeline Improvements(P1-5) Sewer pipelines subject to deteriorated conditions should be replaced to ensure an adequate level of service. Deteriorated sewer pipelines may fail imminently and cause disruption in service and public safety concerns. 3. Repair & Replacements (Groups 1-9) The 2017 Sewer SystemMaster Plan recommended the repair or replacement of sewer pipelines with major structural defects. These replacements and repairs are intended to mitigate existing pipeline issues before complete pipeline failure occurs, which can result in sanitary sewer overflows and property damage. The recommended improvements are grouped and phased based on criticality and proximity to other pipeline projects. Strategic Planning Documents 2017 Sewer SystemMaster Plan

2021-2026 Six Year Capital Improvement Program

Page 62 of 127

Made with FlippingBook Ebook Creator