City of Morgan Hill Fiscal Years 2020- 2022 Recommended Operating and CIP Budgets
CITY OF MORGAN HILL Capital Improvement Program
Expenditure Schedule &Category
Wastewater: 308a08
2020-21
2021-22
2022-23
2023-24
2024-25
2025-26
86360 - Construction
$14,500,000 $14,500,000
86530 - Project Implementation
$50,000 $50,000
$100,000
PROJECT COST
$100,000 $14,500,000 $14,500,000
Funding Source(s)
2020-21
2021-22
2022-23
2023-24
2024-25
2025-26
f641 - Sewer Impact Fund f643 - Sewer CIP Fund
$37,500 $12,500 $50,000
$75,000 $10,875,000 $10,875,000 $25,000 $3,625,000 $3,625,000 $100,000 $14,500,000 $14,500,000
FUNDING TOTALS
Financial Comments Depending upon the exact timing of this project and other Wastewater Impact Fee funded projects, the City may elect to issue bonds to fund it. Estimated Project Schedule Timeframe
In progress FY 2020-21
Planning
Project Design
Right-of-Way Acquisition & Permitting
FY 2021-22
FY 2022-23 FY 2023-24
Construction
Project Closeout
Operating Cost Impacts Investing in the new trunk line ensures the City has capacity for future growth and provides reliability and redundancy while minimizing the risk of sewer overflows.
2021-2026 Six Year Capital Improvement Program
Page 73 of 127
Made with FlippingBook Ebook Creator