Project

Project No.

610000

Water Pipeline Repair and Replacement

Category

Water

Department

Engineering and Utilities

Council Priorities Enhancing Public Safety, Maintaining Fiscal Responsibility

Location

Citywide

Project Description The 2017 Water SystemMaster Plan recommended multiple improvements to mitigate existing water system deficiencies, increase the hydraulic reliability of the existing system, or replace existing pipelines due to poor condition or operational considerations. This project consists of constructing nine water pipeline improvements recommended in the Master Plan over the next five years. The pipeline projects have anticipated completion dates as follows: Spring Avenue, Shady Lane, Holiday Tank Pipeline, and First Street - FY2021/22; Mission View Drive, Hale Avenue Extension, and San Pedro Avenue - FY 2023/24; Manzanita Drive and Racoon Court - FY2024/25. Project Justification The City's 2017 Water SystemMaster Plan outlines the orderly construction of water system infrastructure intended to accommodate future growth, while maintaining adequate levels of service. In order to meet these level of service requirements, the Master Plan recommended the construction of these water pipeline

2021-2026 Six Year Capital Improvement Program

Page 88 of 127