City of Morgan Hill Water System Master Plan 2017
Table 8.1 Unit Costs
Water System Master Plan City of Morgan Hill
PRELIMINARY
Pipelines
Cost 2
Pipe Size
(in)
($/lineal foot)
6
$160
8
$180
10
$207
12
$229
16
$276
18
$297
20
$340
24
$372
30
$412
36
$485
Pump Stations Estimated Pumping Station Project Cost = 2.075*10 (0.7583*log(Q)+3.1951) where Q is in gpm
Pressure Reducing Stations
Size (in)
Cost ($)
3" valve
$47,300
6" valve
$77,400
Storage Reservoirs ($/gallon)
≤1.0 MG
$2.15
1.1 MG-3.0 MG
$1.72
3.1 MG - 5.0 MG
$1.24
> 5 MG
$0.92
Groundwater Wells
800 gpm Capacity
$2,340,000
2/16/2017
Notes:
1. Construction costs estimated using January 2017 ENR CCI of 10,532.
2. Pipeline unit costs based on water main construction estimates provided by
City staff.