Development Services Review. Final Report. Zucker July 2016
via Dropbox software after being finalized by the Director to PC members about four calendar days prior to the meeting.
See our recommendations under the “Planning Commission” heading in the Policy Issues section regarding recommendations earlier distribution of PC agenda packets.
11. The PC will review the project and provide feedback. Staff will convey PC feedback in writing following the meeting.
12. If the applicant has requested Council review, which is rare, the project is placed on a Council agenda and the assigned planner prepares a staff report, which is distributed electronically by the City Clerk prior to the meeting. Staff will convey Council feedback in writing to the applicant following the meeting.
Director Administrative Approval Process
A number of planning applications are approved administratively (e.g., staff and director), but can’t be processed over-the-counter (see Over-the-Counter Approval process above) because they require additional staff and/or environmental analysis (e.g. CEQA) and public notice before a final decision can be rendered.
Applicants have the option of applying for a Conceptual Plan Review (CPR) or Preliminary Plan Review (PPR) before submitting a formal application.
Figure 10 below shows the general steps in the Administrative Director Approval process. A summary of the steps follows in the text below.
Morgan Hill, California
130
Zucker Systems
Made with FlippingBook