Development Services Review. Final Report. Zucker July 2016
DESCRIPTION
PERFORMANCE STANDARD
Plan Review - Residential - Multifamily - < 20 units
90% within 10 business days
Plan Review - Residential - Single Family
90% within 10 business days
Plan Review -Residential - Single Family - Standard Plan
90% within 5 business days
Plan Review - Residential modifications
90% with 5 business days
Plan Review - Minor Permits (P/E/M/S)
90% Over the counter/online
Plan review rechecks
90% within 1/2 of previous turnaround time
Plan Review Quality Control
Monthly
Field Inspection Quality Control
Monthly for every Inspector
Field Inspection
90% next business day
Inspection requests can be received up to one hour before Inspector departs office
Inspection Requests
Inspector call to customer with Estimated Time of Arrival (ETA)
30 minutes prior to arrival
28. Recommendation: The Building Division should adopt the Performance Standards identified in the table above. As referenced in the Technology section of this report, the City is in the fortunate position of being able to establish these performance standards in conjunction with the implementation of the TRAKiT permit system. The reporting capabilities of the system will grant management the ability to effectively track and report on the City’s ongoing ability to meet these performance standards. The true value of establishing and monitoring performance standards lies in affording management the ability to balance resources against the constantly fluctuating demand for services. The performance standard should be visualized as a constant. Management’s task is to adjust available resources in response to changing demands for service such that the performance standard can be maintained. The figure below helps illustrate this relationship.
Morgan Hill, California
42