FY 2018-19 and 2019-20 Adopted Operating and CIP Budget
CITY OF MORGAN HILL CAPITAL IMPROVEMENT PROGRAM
Project
Project No.
603000
New Water Mains
Category
Water
Department
Engineering & Utilities
Council Priorities Enhancing Public Safety, Protecting the Environment
Location
Citywide
Project Description The 2017 Water System Master Plan recommended the installation of new water mains to relieve water system deficiencies and increase the hydraulic reliability of the system.
Project Justification The City's 2017 Water System Master Plan (the Master Plan) outlines the orderly construction of water system infrastructure intended to accommodate future growth, while maintaining adequate levels of service. In order to meet these levels of service requirements, the Master Plan recommended the construction of these water pipeline improvements to mitigate capacity deficiencies, increase hydraulic reliability, and account for existing operational considerations. These pipeline improvements will provide adequate levels of service for existing customers. The cost for these pipelines will be met with funds provided by development charges.
Strategic Planning Documents 2017 Water System Master Plan
2019-2024 Six-Year Capital Improvement Program
PAGE: 107 OF 152