FY 2018-19 and 2019-20 Adopted Operating and CIP Budget
CITY OF MORGAN HILL CAPITAL IMPROVEMENT PROGRAM
Expenditure Schedule & Category
Water: 610b18
2018-19
2019-20
2020-21
2021-22
2022-23
2023-24
86200 - Professional Services
$88,462
$44,231
$44,231
86360 - Construction
$342,538
$385,769
$435,769
86530 - Project Implementation
$19,000
$20,000
$20,000
PROJECT COST
$450,000
$450,000
$500,000
Funding Source(s)
2018-19
2019-20
2020-21
2021-22
2022-23
2023-24
f653 - Water CIP Fund
$450,000
$450,000
$500,000
FUNDING TOTALS
$450,000
$450,000
$500,000
Estimated Project Schedule
Timeframe
Planning
Complete
Construction
Annually
Project Closeout
Annually
Operating Cost Impacts This project does not increase operating costs.
2019-2024 Six-Year Capital Improvement Program
PAGE: 114 OF 152