FY 2018-19 and 2019-20 Adopted Operating and CIP Budget

CITY OF MORGAN HILL CAPITAL IMPROVEMENT PROGRAM

309 - Traffic Impact

Fund Description Traffic Impact Fund revenues are received from developers if their projects have an adverse impact on traffic flows, streets, etc. The funds collected may be expended on new streets, traffic signals, and improvements of existing streets where they are impacted by new development. Fund is subject to the restrictions of AB1600. How this Fund Generates Money for Capital Investment Revenues result from the City's development impact fee program, through which new development pays the capital costs associated with growth. New development creates the need for the City to expand its inventory of public facilities and build new, or add on to current, infrastructure to handle the demands of new services. The City imposes public facilities fees under authority granted by the Mitigation Fee Act (the Act), contained in California Government Code Sections 66000 et seq. A City Council-adopted "Impact Fee Report" provides the necessary findings required by the Act for adoption of the fees presented in impact fee schedules. Limitations and Other Important Factors All development impact fee-funded capital projects are programmed through the City's 6-Year CIP, by which the City identifies and directs its fee revenue to new public facilities/infrastructure projects that will accommodate future growth. By programming fee revenues to specific capital projects, the City ensures a reasonable relationship between new development and the use of fee revenues as required by the Act. Goals for Capital Investment The goal for this fund during this period is to expand transit and non-motorized travel opportunities as needed to service anticipated future growth, including the Hale Avenue Extension Project. Expenditures-Other include a transfer to the General Plan Update.

Revenues-Other include grant funding from the County for the Hale Avenue Extension project attributed to Measure B.

Project List Summary

Projects

2018-19

2019-20

2020-21

2021-22

2022-23

2023-24

502000 - Intersection Improvements

$1,500,000

546007 - Hale Avenue Extension

$19,650,000

$310,000

Totals $19,650,000

$310,000

$1,500,000

2019-2024 Six-Year Capital Improvement Program

PAGE: 135 OF 152

Made with FlippingBook - Online magazine maker