FY 2021 2122 ADOPTED OPERATING AND FY 2021 2526 CIP BUDGETS
CITY OF MORGAN HILL Capital Improvement Program
Expenditure Schedule &Category
Public Facilities: 231018
2020-21
2021-22
2022-23
2023-24
2024-25
2025-26
86200 - Professional Services
$85,000
$171,148
$5,350,000
86360 - Construction
86530 - Project Implementation
$25,000 $110,000
$48,852
$150,000
$150,000 $150,000
PROJECT COST
$220,000 $5,500,000
Funding Source(s)
2020-21
2021-22
2022-23
2023-24
2024-25
2025-26
f313 - Fire Impact Fund
$110,000
$220,000 $3,800,000
$150,000
f315 - Public Safety Facilities Impact
$1,700,000
FUNDING TOTALS
$110,000
$220,000 $5,500,000
$150,000
Financial Comments The current budget funds construction of the Fire Station, but the addition of citywide traffic preemption is not funded within the project due to fiscal limitations. Estimated Project Schedule Timeframe
FY 2020/21 FY 2021/22 FY 2022/23 FY 2023/24
Planning
Project Design Construction Project Closeout
Operating Cost Impacts Adding a third Fire Station will create considerable costs to operate and will be discussed in detail within the Fire Department Operating Budget.