FY 2021 2122 ADOPTED OPERATING AND FY 2021 2526 CIP BUDGETS
CITY OF MORGAN HILL Capital Improvement Program
Expenditure Schedule &Category
Storm Drainage: 417099
2020-21
2021-22
2022-23
2023-24
2024-25
2025-26
86360 - Construction
$2,300,000 $1,700,000
86530 - Project Implementation
$200,000 $300,000 PROJECT COST $2,500,000 $2,000,000
Funding Source(s)
2020-21
2021-22
2022-23
2023-24
2024-25
2025-26
f303 - Drainage Impact Fund
$2,500,000 $2,000,000 FUNDING TOTALS $2,500,000 $2,000,000
Financial Comments Estimated Project Schedule
Timeframe
Complete Complete
Planning
Project Design
Right-of-Way Acquisition & Permitting
Complete
Under construction
Construction
FY 2022/23 for funded portions of the project
Project Closeout
Operating Cost Impacts Costs to operate and maintain the Upper Llagas Creek Flood Protection Project will be borne by the Santa Clara Valley Water District. Costs to maintain local drainage facilities constructed in FY's 18-19 through 20-21 will be borne by the City. Those costs are unknown at this time but will likely be off-set by a reduction in O&M costs due to elimination of flooding in streets, once projects are completed.
2021-2026 Six Year Capital Improvement Program
Page 44 of 124
Made with FlippingBook - professional solution for displaying marketing and sales documents online