FY 2021 2122 ADOPTED OPERATING AND FY 2021 2526 CIP BUDGETS
CITY OF MORGAN HILL Capital Improvement Program
Trash Compliance
Project
Project No.
418020
Category
Storm Drainage
Department
Community Services
Council Priorities Protecting the Environment, Maintaining Infrastructure, Fiscal Sustainability
Location
City Wide
Project Description On April 7, 2015, the State Water Resources Control Board (SWRCB) adopted the Statewide Trash Provisions which address the impacts trash has on the beneficial uses of surface waters. The Trash Provisions establish a statewide water quality objective for trash and a prohibition of trash discharge. This is a State-mandated activity that must be completed if the City is to avoid punitive fines. The City is required to demonstrate 100 percent compliance with the Trash Provisions by the Year 2030. Full compliance with the Trash Provisions requires the City to install, operate, and maintain State-certified Full Capture System (FCS) devices that capture all trash down to 5 millimeters in size from defined Priority Land Use areas. These include all industrial, commercial, mixed-use, high-density residential and public transportation station areas. Initial costs for complying with the Trash Provisions will depend on the types of FCS devices selected, size (large vs. small), installation costs, and the total number of devices installed. The type and number of FCS devices installed will depend on Priority Land Uses and the stormwater infrastructure that serves those areas. Other long-term cost considerations include maintenance and replacement of the FCS devices which will depend on the qualities of the drainage areas filtering through the devices including acreage, land use, perviousness, flow rates, etc.
2021-2026 Six Year Capital Improvement Program
Page 45 of 124