Streets & Roads: 546007
2020-21
2021-22
2022-23
2023-24
2024-25
2025-26
86360 - Construction
$16,239,645
86530 - Project Implementation
$260,355
$300,000
$200,000
PROJECT COST $16,500,000
$300,000
$200,000
Funding Source(s)
2020-21
2021-22
2022-23
2023-24
2024-25
2025-26
f303 - Drainage Impact Fund
$2,000,000
f309 - Traffic Impact Fund
$14,500,000
$300,000 $300,000
$200,000 $200,000
FUNDING TOTALS $16,500,000
Financial Comments The project was prioritized for funding from the 2016 County-wide Measure B initiative. Funding for the design and land acquisition was funded through Traffic Impact Fees. The majority of the funding for the project will come from Measure B funds through the Santa Clara Valley Transportation Authority. Additionally, a limited amount of funding will come from Traffic Impact Fees and from Storm Drain Impact Fees (associated with new storm drain improvements), based on the award of Measure B funding. Estimated Project Schedule Timeframe
Complete Complete
Planning
Project Design
Right-of-Way Acquisition & Permitting
Complete
Fall 2020 through Fall 2022
Construction
FY 2022/23
Project Closeout
Operating Cost Impacts Additional lane miles will be added to the street maintenance inventory. One new traffic signal at West Main Avenue/Hale Avenue will also be added to the streets inventory.
2021-2026 Six Year Capital Improvement Program
Page 55 of 124