FY 2021 2122 ADOPTED OPERATING AND FY 2021 2526 CIP BUDGETS
CITY OF MORGAN HILL Capital Improvement Program
Expenditure Schedule &Category
Wastewater: 302t17
2020-21
2021-22
2022-23
2023-24
2024-25
2025-26
86360 - Construction
$725,000
86530 - Project Implementation
$75,000
PROJECT COST
$800,000
Funding Source(s)
2020-21
2021-22
2022-23
2023-24
2024-25
2025-26
f643 - Sewer CIP Fund
$800,000 $800,000
FUNDING TOTALS
Financial Comments The project will be funded through bond proceeds and repaid by Wastewater ratepayers and impact fees. Estimated Project Schedule
Timeframe
Complete In Progress FY 2021/22 FY 2021/22
Planning
Project Design Construction Project Closeout
Operating Cost Impacts Increasing the capacity of these pipelines will minimize the risk of sewer overflows and reduces the City's exposure to high cost emergency repairs.
2021-2026 Six Year Capital Improvement Program