FY 2021 2122 ADOPTED OPERATING AND FY 2021 2526 CIP BUDGETS
CITY OF MORGAN HILL Capital Improvement Program
Project
Project No.
308a08
New Trunk Line
Category
Wastewater
Department
Engineering & Utilities
Council Priorities Enhancing Public Safety, Maintaining Fiscal Responsibility
Location
Morgan Hill to SCRWA Treatment Plant
Project Description All of Morgan Hill's wastewater is delivered to the wastewater treatment plant in Gilroy via a single trunk sewer line that extends south from the City. The construction of a new parallel sewer trunk line is intended to facilitate the City's planned growth and to mitigate capacity constrictions in the existing trunk line. The project will span the distance between Highland Avenue and Renz Lane in Gilroy. The design is scheduled for completion in 2020. Commencement of construction is anticipated in the Summer of 2022. Project Justification The City's Sewer SystemMaster Plan identified areas of growth consistent with the General Plan and includes the orderly construction of sewer improvements intended to service that growth. The rate of growth drives the need for expanded capacity in the sewer trunk line and the capacity of the SCRWA treatment plant. Cost for expanding capacity of the trunk line will be met by the collection of sewer impact fees and existing rates.
Strategic Planning Documents 2017 Sewer System Master Plan
2021-2026 Six Year Capital Improvement Program
Page 69 of 124