FY 2021 2122 ADOPTED OPERATING AND FY 2021 2526 CIP BUDGETS
CITY OF MORGAN HILL Capital Improvement Program
New/Replacement Sewer Lines
Project
Project No.
315006
Category
Wastewater
Department
Engineering & Utilities
Council Priorities Enhancing Public Safety, Maintaining Fiscal Responsibility
Location
Citywide
Project Description The Sewer Capacity projects are intended to provide for the expansion of the sewer system infrastructure to maintain service levels and prepare for future growth requirements.
Key geographic areas have been identified for this effort which include: 1. Dunne Avenue fromMurphy Avenue to Condit Road 2. LaCrosse Drive between LaMar Drive &Monterey Road 3. Llagas Creek Drive- Eagle Springs to Hale Avenue
1. Dunne Avenue fromMurphy Avenue to Condit Road This project consists of replacing 950 feet of existing 8-inch sewer pipeline along Dunne Avenue with a new 10- inch sewer pipeline from 230 feet east of Murphy Avenue to Condit Road. This project is intended to accommodate additional flows contributed by residential development east of Highway 101. 2. LaCrosse Drive between LaMar Drive &Monterey Road This project consists of replacing 1,700 feet of existing 10-inch sewer pipeline with a new 12-inch sewer pipeline along La Cross Drive/Vineyard Boulevard between La Mar Drive and Monterey Road. The 2017 Sewer System Master Plan indicated the capacity of the existing 10-inch sewer pipeline is insufficient under existing peak flow
2021-2026 Six Year Capital Improvement Program
Page 71 of 124
Made with FlippingBook - professional solution for displaying marketing and sales documents online