FY 2021 2122 ADOPTED OPERATING AND FY 2021 2526 CIP BUDGETS
CITY OF MORGAN HILL Capital Improvement Program
Expenditure Schedule &Category
Water: 603000
2020-21
2021-22
2022-23
2023-24
2024-25
2025-26
86220 - Architecture and Design
$100,000
86360 - Construction
$550,000
86530 - Project Implementation
$50,000
PROJECT COST
$100,000
$600,000
Funding Source(s)
2020-21
2021-22
2022-23
2023-24
2024-25
2025-26
f651 - Water Impact Fund
$100,000 $100,000
$600,000 $600,000
FUNDING TOTALS
Financial Comments
Estimated Project Schedule
Timeframe
FY 2020-21 FY 2021-22 FY 2021-22
Project Design Construction Project Closeout
Operating Cost Impacts This project does not increase operating costs.
2021-2026 Six Year Capital Improvement Program
Page 82 of 124
Made with FlippingBook - professional solution for displaying marketing and sales documents online