FY18-19 and 19-20 RECOMMENDED OPERATING AND CIP BUDGET - FIN
CITY OF MORGAN HILL CAPITAL IMPROVEMENT PROGRAM
Expenditure Schedule & Category
Wastewater: 302m15
2018-19
2019-20
2020-21
2021-22
2022-23
2023-24
86530 - Project Implementation
$25,000 $25,000
PROJECT COST
Funding Source(s)
2018-19
2019-20
2020-21
2021-22
2022-23
2023-24
f643 - Sewer CIP Fund
$25,000 $25,000
FUNDING TOTALS
Estimated Project Schedule
Timeframe
Planning
Complete Complete
Project Design Construction Project Closeout
Quarter 1 of FY 2018/19 Quarter 2 of FY 2018/19
Operating Cost Impacts These improvements will improve the condition of the sewer system and therefore reduce time spent for maintenance.
2019-2024 Six-Year Capital Improvement Program
PAGE: 83 OF 152