Adopted Capital Improvement Program Budget FY 2024-25 through FY 2029-30
City of Morgan Hill Capital Improvement Program FY 2024-25 – FY 2029-30
Project Name: West Little Llagas Creek Trail
Project No. PR1002
Project Location
Financial Comments The City plans to apply for grant funding to fund the majority of the project improvements but needs to fund the environmental work for the southern phase to be eligible for grants in this area.
Along West Little Llagas Creek
Operating Cost Impacts This facility will increase Park Maintenance operating costs in the General Fund by approximately $10,000- $25,000 annually for landscape maintenance, weed control, tree trimming, utilities, occasional trail minor
repair work, graffiti/vandalism, and repair/replacement of trail benches.
Expenditure Schedule Annual Expenditures
2024-25
2025-26
2026-27
2027-28
2028-29
2029-30
Fund-301
150,000
150,000
- - -
- - -
- - -
- - -
$ 150,000
$ 150,000
Project Cost
Estimated Project Schedule
Timeline for Completion
In Progress, to be completed in FY 2024-25
Planning
FY 2024-25 and future years
Project Design
Right of Way/ Acquisition/Permitting
To be determined if needed
Phase 1 FY2025-26, Future phases in future years To be determined depending on project phasing
Construction
Project Close-out