Adopted Capital Improvement Program Budget FY 2024-25 through FY 2029-30
City of Morgan Hill Capital Improvement Program FY 2024-25 – FY 2029-30 Project No. PR1008
Project Name: Villa Mira Monte
Project Location
Financial Comments Funding for this project is included in the CIP budget within the Community/Recreation Center Impact Fund (360).
Villa Mira Monte
Operating Cost Impacts The City currently provides $20,000 per year in support to the Historical Society's operations of Villa Mira Monte. The enhancements will be designed to support improved operations and maintenance at the site, so no additional operational costs are anticipated for the City in relation to this project. The partnership between the City and the Historical Society has long benefitted the financial maintenance of the facility, but the vast majority of the operations at the site is accomplished by utilizing volunteers and fundraising.
Pro Mira Mon Expenditure Schedule Annual Expenditures
2024-25
2025-26
2026-27
2027-28
2028-29
2029-30
Fund-360
350,000
3,500,000
-
-
-
-
$ 350,000
$ 3,500,000
-
-
-
-
Project Cost
Estimated Project Schedule
Timeline for Completion
Complete FY 2024-25
Planning
Project Design
Right of Way/ Acquisition/Permitting
Not applicable
FY 2025-26 & 2026-27
Construction
Project Close-out
FY 2026-27