Project Name: Storm System Repairs and Improvements
Project No. SD4002
Project Location
Financial Comments The funding source for these localized drainage projects has been the drainage fees in Local Drainage (Non-AB 1600) Fund (304), which was collected from residential developer fees as part of the Residential Development Control System (RDCS) competition . Due to its elimination via State legislation, no new revenue will be received. Funds are programmed in the next six years, spending down the fund balance to accomplish projects.
Citywide
Operating Cost Impacts As local drainage problems are repaired or improved, maintenance costs are reduced during rain events.
Expenditure Schedule Annual Expenditures
2024-25
2025-26
2026-27
2027-28
2028-29
2029-30
Fund-304
250,000
250,000
100,000
100,000
100,000
100,000
$ 250,000
$ 250,000
$ 100,000
$ 100,000
$ 100,000
$ 100,000
Project Cost
Estimated Project Schedule
Timeline for Completion
Ongoing
Planning
Annually as needed
Project Design
Right of Way/ Acquisition/Permitting
Not applicable
Construction
Annually for identified projects Annually following construction
Project Close-out