Adopted Capital Improvement Program Budget FY 2024-25 through FY 2029-30
City of Morgan Hill Capital Improvement Program FY 2024-25 – FY 2029-30
Project Name: Citywide Small Trash Capture Project
Project No. SD4007
Project Location
Financial Comments The project shall be funded from implementation funds from the City’s solid waste franchise.
Citywide
Operating Cost Impacts The City shall utilize storm water trash capture implementation funds and request through the City’s solid waste franchise to fund the significant expenses associated with this State mandate. Operating costs are estimated at $150,000 annually for management of trash capture devices throughout the City.
Expenditure Schedule Annual Expenditures
2024-25
2025-26
2026-27
2027-28
2028-29
2029-30
Fund-304
240,000
-
-
-
-
-
$ 240,000
-
-
-
-
-
Project Cost
Estimated Project Schedule
Timeline for Completion
Complete
Planning
In progress to be complete FY 2024-25
Project Design
Right of Way/ Acquisition/Permitting
Not applicable
Construction
FY 2024-25 FY 2025-26
Project Close-out