Adopted Capital Improvement Program Budget FY 2024-25 through FY 2029-30
City of Morgan Hill Capital Improvement Program FY 2024-25 – FY 2029-30
Project Name : Downtown Parking Trash Enclosures
Project No. SR5012
Project Location
Financial Comments Private businesses shall be required to pay back the City for this improvement.
Third Street
Operating Cost Impacts Operating costs for the trash enclosure are paid by the businesses utilizing the enclosure.
Expenditure Schedule Annual Expenditures
2024-25
2025-26
2026-27
2027-28
2028-29
2029-30
Fund-346
35,000
-
-
-
-
-
$ 35,000
-
-
-
-
-
Project Cost
Estimated Project Schedule
Timeline for Completion
In progress FY 2024-25
Planning
Project Design
Right of Way/ Acquisition/Permitting
FY 2024-25
FY 2024-25 FY 2025-26
Construction
Project Close-out