Adopted Capital Improvement Program Budget FY 2024-25 through FY 2029-30
City of Morgan Hill Capital Improvement Program FY 2024-25 – FY 2029-30
Project Name: Sewer Plant Improvements
Project No. WW3004
Project Location
Financial Comments Funding for the projects outlined is allocated in the Sewer Impact Fund (641).
SCRWA Treatment Plant, Gilroy
Operating Cost Impacts Operating costs impacts are not anticipated to increase significantly from future projects at the treatment plant.
Expenditure Schedule Annual Expenditures
2024-25
2025-26
2026-27
2027-28
2028-29
2029-30
Fund-641
-
1,500,000
-
-
2.500,000
-
$ 1,500,000
$ 2,500,000
-
-
-
-
Project Cost
Estimated Project Schedule
Timeline for Completion
Ongoing
Planning
FY 2025-26 & FY2028-29
Project Design
Right of Way/ Acquisition/Permitting
Not applicable
Construction
FY 2025-26 to FY2026-27 & FY2028-29 to FY2029-30
Project Close-out
FY 2026-27 & FY 2029-30