Project Name: Groundwater Wells
Project No. WA6001
Project Location
Financial Comments All the funding for the new groundwater well projects is from impact fees - Water Impact Fund (651) and water rates collected - Water Capital Project Fund (653).
Boys Ranch Wells and Nob Hill Wells
Operating Cost Impacts These projects will increase operation and maintenance costs which will be accounted for by increased water sales, increased customers, and/or increased water rates.
Expenditure Schedule Annual Expenditures
2024-25
2025-26
2026-27
2027-28
2028-29
2029-30
Fund-651 Fund-653
1 00,000
5,000,000
-
-
-
600,000
4 ,600,000 Project Cost $ 4,7 00,000 $ 5,000,000
$ 600,000
-
-
-
Estimated Project Schedule
Timeline for Completion
Ongoing
Planning
NH-W1 (Summer 2024), BR-W1(Spring 2025), NH-W2 (Fall 2029), BR-W2 (Fall 2029) NH-W1 (Summer 2024), BR-W1(Spring 2025), NH-W2 (Spring 2030), BR-W2 (Spring 2030) NH-W1 (Fall 2025), BR-W1(Fall 2026), NH-W2 (Fall 2030), BR-W2 (Fall 2030) NH-W1 (Fall 2025), BR-W1(Fall 2026), NH-W2 (Fall 2031), BR-W2 (Fall 2031)
Project Design
Right of Way/ Acquisition/Permitting
Construction
Project Close-out