FY 2018-19 and 2019-20 Adopted Operating and CIP Budget
CITY OF MORGAN HILL CAPITAL IMPROVEMENT PROGRAM
Project
Project No.
315006
Sewer Capacity Improvement Projects
Category
Wastewater
Department
Engineering & Utilities
Council Priorities Enhancing Public Safety, Maintaining Fiscal Responsibility
Location
Citywide
Project Description The Sewer Capacity projects are intended to provide for the expansion of the sewer system infrastructure to
maintain service levels and prepare for future growth requirements. Key geographic areas have been identified for this effort which include:
1. Dunne Avenue fromMurphy Avenue to Condit Road 2. LaCrosse Drive between LaMar Drive & Monterey Road 3. Along Northbound Highway 101, North of Cochrane 4. Llagas Creek Drive- Eagle Springs to Hale Avenue
1. Dunne Avenue fromMurphy Avenue to Condit Road This project consists of replacing 950 feet of existing 8-inch sewer pipeline along Dunne Avenue with a new 10- inch sewer pipeline from 230 feet east of Murphy Avenue to Condit Road. This project is intended to accommodate additional flows contributed by residential development east of Highway 101. 2. LaCrosse Drive between LaMar Drive & Monterey Road This project consists of replacing 1,700 feet of existing 10-inch sewer pipeline with a new 12-inch sewer pipeline along La Cross Drive/Vineyard Boulevard between La Mar Drive and Monterey Road. The 2017 Sewer System Master Plan indicated the capacity of the existing 10-inch sewer pipeline is insufficient under existing peak flow conditions and this project is intended to mitigate the capacity deficiency. This project will also provide additional capacity to accommodate additional flows contributed by future developments west of Monterey Road.
2019-2024 Six-Year Capital Improvement Program
PAGE: 96 OF 152