CITY OF MORGAN HILL CAPITAL IMPROVEMENT PROGRAM

3. Along Northbound Highway 101, North of Cochrane This project consists of replacing 1,200 feet of existing 10-inch sewer pipeline along NB US 101 north of Cochrane Road. This project is necessary to accommodate additional flows contributed by planned residential development east of Cochrane Road and north of Peet Road. 4. Llagas Creek Drive- Eagle Springs to Hale Avenue This project consists of replacing 1,950 feet of existing 8-inch sewer pipeline along Llagas Creek Drive from Eagle Springs Court to Hale Avenue. The 2017 Sewer SystemMaster Plan indicated the existing 8-inch sewer pipeline is nearing maximum capacity and recommended the replacement of this pipeline to accommodate additional flows contributed by planned residential developments west of Hale Avenue.

Project Justification The City's 2017 Sewer System Master Plan outlines the orderly construction of sewer infrastructure intended to accommodate future growth, while maintaining adequate levels of service. In order to meet these levels of service requirements, the Master Plan recommended the replacement and upsize of the pipelines to meet the growing capacity needs of the sewer system. This increase in sewer system capacity will allow for the planned development as specified in the City's General Plan. The cost for this pipeline replacement will be met with a combination of sewer collection system rates and impact fees from new development.

Strategic Planning Documents 2017 Sewer System Master Plan

2019-2024 Six-Year Capital Improvement Program

PAGE: 97 OF 152

Made with FlippingBook - Online magazine maker