CITY OF MORGAN HILL CAPITAL IMPROVEMENT PROGRAM

Project

Project No.

620b18

Holiday Tank Repair #2

Category

Water

Department

Engineering & Utilities

Council Priorities Enhancing Public Safety, Protecting the Environment

Location

Existing Holiday Tank #2

Project Description This project includes ongoing repairs to the existing Holiday Lake #2 water storage tank. These improvements are intended to extend the service life of the water storage tank and continue to provide an adequate level of service to existing water system customers.

Project Justification These improvements are intended to extend the service life of the Holiday Lake #2 water storage tank and provide an adequate level of service to existing water system customers.

Strategic Planning Documents 2017 Water System Master Plan

2019-2024 Six-Year Capital Improvement Program

PAGE: 119 OF 152