CITY OF MORGAN HILL CAPITAL IMPROVEMENT PROGRAM

Expenditure Schedule & Category

Water: 620b18

2018-19

2019-20

2020-21

2021-22

2022-23

2023-24

86200 - Professional Services

$15,923

86360 - Construction

$69,231

86530 - Project Implementation

$5,000

PROJECT COST

$90,154

Funding Source(s)

2018-19

2019-20

2020-21

2021-22

2022-23

2023-24

f653 - Water CIP Fund

$90,154

FUNDING TOTALS

$90,154

Estimated Project Schedule

Timeframe

Planning

FY 2018/19

Construction

FY 2018/19

Project Closeout

FY 2019/20

Operating Cost Impacts This project does not increase operating costs.