Adopted Capital Improvement Program Budget FY 2024-25 through FY 2029-30
City of Morgan Hill Capital Improvement Program FY 2024-25 – FY 2029-30
Project Name: Water Pipeline Repair and Replacement
Project No. WA6005
P roject Location
Financial Comments The cost for these pipeline replacements will be met with funds provided by water system rates from the Water Capital Project Fund (653).
Citywide
Operating Cost Impacts These projects will have positive impacts on operating costs by proactively replacing water mains before they fail and require emergency response.
Expenditure Schedule Annual Expenditures
2024-25
2025-26
2026-27
2027-28
2028-29
2029-30
Fund-653
1 , 0 00,000
2,000,000
1,000,000
2,000,000
2,500,000
3,000,000
Project Cost $ 1 , 0 00,000 $ 2,000,000 $ 1,000,000 $ 2,000,000 $ 2,500,000 $ 3,000,000
Estimated Project Schedule
Timeline for Completion
On-going
Planning
Summer to Fall (Every Year)
Project Design
Right of Way/ Acquisition/Permitting
Winter (Following Every Year)
Construction
Winter to Fall (Same Year)
Project Close-out
Fall (Same Year)