Project Name: Reservoir Recoating and Rehabilitation
Project No. WA6009
Project Location
Financial Comments Funding for the recoating improvement projects is from the Water Capital Project Fund (653) and paid for by water ratepayers.
Various - Citywide
Operating Cost Impacts This project does not increase operating costs.
Expenditure Schedule Annual Expenditures
2024-25
2025-26
2026-27
2027-28
2028-29
2029-30
Fund-653
1,000,000
2,500,000
2,000,000
-
-
-
Project Cost $ 1,000,000 $ 2,500,000 $ 2,000,000
-
-
-
Estimated Project Schedule
Timeline for Completion
RC-1 (Fall 24), RC-3 (Winter 25), RC-4 (Winter 25), RC-5, & RC-6 (Winter 28) RC-1 (Fall 24), RC-3 (Winter 25), RC-4 (Winter 25), RC-5 &RC-6 (Winter 28)
Planning
Project Design
Right of Way/ Acquisition/Permitting
Not applicable
RC-1 (Spring 25), RC-3 (Spring 25), RC-4 (Spring 26), RC-5 & RC-6 (Fall 29) RC-1 (Spring 25), RC-3 (Spring 25), RC-4 (Spring 26), RC-5 & RC-6 (Fall 29)
Construction
Project Close-out