City of Morgan Hill Capital Improvement Program FY 2024-25 – FY 2029-30
Project Name: New Fire Stations
Project No. PF2003
Project Location
Financial Comments The Fire Station is being funded through Public Safety Facility Impact Fees that have been collected and will continue to be collected over the next decade. To support the construction, interfund loans from multiple other funds are being utilized to support the immediate construction of the facility. Prior to FY2024-25, $11.25M had been appropriated for the Fire Station and associated vehicles/equipment.
17285 Butterfield Blvd.
Operating Cost Impacts Operating costs for the Third Fire Station are significant and outlined in the Fire Department’s operating budget for FY 2024-25 and FY 2025-26.
Expenditure Schedule Annual Expenditures
2024-25
2025-26
2026-27
2027-28
2028-29
2029-30
Fund-315
950,000
-
-
-
-
-
$ 950,000
-
-
-
-
-
Project Cost
Estimated Project Schedule
Timeline for Completion
Completed
Planning
Completed 2023
Project Design
Right of Way/ Acquisition/Permitting
Completed 2023
Construction
Fall 2023 – Fall 2024
Project Close-out
Fall 2024