Adopted Capital Improvement Program Budget FY 2024-25 through FY 2029-30
City of Morgan Hill Capital Improvement Program FY 2024-25 – FY 2029-30
Project Name: Transportation Master Plan Projects
Project No. SR5011
P roject Location
Financial Comments The use of traffic impact fees for projects identified in the P lan will need to identify a nexus to new development, which is charged these fees. An updated fee study will be completed with the Transportation Master Plan, which is currently in progress. Operating Cost Impacts Operating cost impacts for the Transportation Master Plan identified improvements are currently unknown.
Citywide
Expenditure Schedule Annual Expenditures
2024-25
2025-26
2026-27
2027-28
2028-29
2029-30
Fund-309
-
250,000
4,000,000
250,000
250,000
2,000,000
$ 250,000
$ 4,000,000
$ 250,000
$ 250,0000 $ 2,000,000
-
Project Cost
Estimated Project Schedule
Timeline for Completion
Currently Underway
Planning
FY 2025-26
Project Design
Right of Way/ Acquisition/Permitting
To be determined
Construction
FY 2026-27, Fy2029-30
Project Close-out
To be determined