Adopted Capital Improvement Program Budget FY 2024-25 through FY 2029-30
City of Morgan Hill Capital Improvement Program FY 2024-25 – FY 2029-30
Project Name: Utility Infrastructure Access Roads
Project No. WW3010
Project Location
Financial Comments This project will be funded through wastewater and water rates based on the purpose of the access roads.
Jackson Oaks, Oakwood Court, Thomas Grade
Operating Cost Impacts This project will reduce maintenance requirements and create a safer work environment, reducing overall operating costs.
Expenditure Schedule Annual Expenditures
2024-25
2025-26
2026-27
2027-28
2028-29
2029-30
Fund-643 Fund-653
-
- - -
500,000
- - -
- - -
500,000
550,000 $ 550,000
-
-
$ 500,000
$ 500,000
Project Cost
Estimated Project Schedule
Timeline for Completion
In progress
Planning
Summer 2025
Project Design
Right of Way/ Acquisition/Permitting
Not applicable
Construction
Fall 2027, Fall 2030 Fall 2027, Fall 2030
Project Close-out